Hospital Facilities

Dáil Éireann Debate, Wednesday - 13 January 2021

Wednesday, 13 January 2021

Questions (776)

Pádraig O'Sullivan

Question:

776. Deputy Pádraig O'Sullivan asked the Minister for Health the funding that has been allocated or made available for the building of an extension to a facility (details supplied) which will provide an additional 60 beds; and if he will make a statement on the matter. [44751/20]

View answer

Written answers

The Department have been advised by the Estates Division of the Health Service Executive who are responsible for the delivery of public healthcare infrastructure projects, that the HSE expect to commence construction work on the 60 bed extension to Heather House in early 2021.

Completion of the project is expected in Q4 2021. The estimated project cost is €27m approx.