Dáil Éireann Debate, Wednesday - 27 January 2021

Wednesday, 27 January 2021

Questions (462)

Jackie Cahill

Question:

462. Deputy Jackie Cahill asked the Minister for Education the reason for the delay in respect of the commencement of building works on the autism spectrum disorder, ASD, unit at a school (details supplied); and if she will make a statement on the matter. [4085/21]

View answer

Written answers

The Deputy will be aware that the project to which he refers was approved to go to Tender in June 2020.

Since this approval, a submission for additional fees for works outside the original scope were submitted and recently assessed by my Department's Technical team. My Department has sought clarification with the school on these extra fees and awaits the school's response to same.