Dáil Éireann Debate, Thursday - 4 February 2021

Thursday, 4 February 2021

Questions (20)

Sorca Clarke

Question:

20. Deputy Sorca Clarke asked the Minister for the Environment, Climate and Communications the current timeline under the National Broadband Plan for the roll-out of a fibre connection to a premises (details supplied). [6254/21]

View answer

Written answers

The Question  refers  to a premises located in the AMBER area on the National Broadband Plan (NBP) High Speed Broadband Map which is available on my Department's website www.broadband.gov.ie. The AMBER area represents the area to be served by the network to be deployed under the NBP State led intervention. I am advised by National Broadband Ireland that, as of 26 January 2021, over 166,000 premises across all counties have been surveyed. Surveys in County Longford have been completed in Drumlish, Ennybegs, Moat Farrell, Cullyfad, Longford Town, Newtownforbes, Cloondara, Stonepark, Ardagh, Moydow and Kilashee. Further details are available on specific areas within County Longford through the NBI website which provides a facility for any premises within the intervention area to register their interest in being provided with deployment updates through its website www.nbi.ie. Individuals who register with this facility will receive regular updates on progress by NBI on delivering the network and specific updates related to their own premises as works commence. I am advised that NBI is working to provide more detail on its website, with a rolling update on network build plans. NBI also has a dedicated email address, reps@nbi.ie, which can be used by Oireachtas members for specific queries.

Broadband Connection Points (BCPs) are a key element of the NBP providing high speed broadband in every county in advance of the roll out of the fibre to the home network. As of 30 January, 178 publicly accessible BCP sites have been installed by NBI and the high speed broadband service will be switched on in these locations through service provider contracts managed by the Department of Rural and Community Development. BCP’s are installed at Colmcille GAA Club, Ballymore Shamrocks GAA Club, Mullinalaghta Community Centre, Corlea Heritage Centre and Aughine Community Centre. Further details can be found at https://nbi.ie/bcp-locations/. 

Naomh Guasachta National School (Bunlahy) has been installed by NBI and  Fermoyle National School has been connected for educational access as part of this initiative. My Department continues to work with the Department of Education to prioritise schools with no high speed broadband, within the Intervention Area, for connection over the term of the NBP. In this regard, an acceleration of this aspect of the National Broadband Plan was announced in December which will see some 679 primary schools connected to high speed broadband by 2022, well ahead of the original target delivery timeframe of 2026. Further details are available on the NBI website at https://nbi.ie/primary-schools-list/.