255. Deputy Gary Gannon asked the Minister for Public Expenditure and Reform the status of Fitzgibbon Street Garda station; if the second phase of works is currently on schedule to be completed in March 2021; and if he will make a statement on the matter. [7440/21]

View answer

Written answers (Question to Public)

The refurbishment works at Fitzgibbon St Garda Station were on schedule to be completed in March 2021, however, works were suspended on site from 6pm 8th January 2021 in accordance with the current Covid-19 restrictions. A revised completion date will be provided when the current restrictions on construction works are removed.