1310. Deputy Matt Shanahan asked the Minister for Further and Higher Education, Research, Innovation and Science if he will provide a schedule of each institution, building name, size and funding requested under the Higher Education Strategic Infrastructure Fund programme call issued in December 2018 and announced in August 2019, in tabular form; and if he will make a statement on the matter. [19233/21]

View answer

Written answers

I can advise the Deputy that 15 applications were received under the Higher Education Strategic Infrastructure Fund. Five major capital projects were approved for co-funding under the Fund. The total co-funding approved amounts to €96.6m.

The 15 projects are listed in the table with the approved projects highlighted in bold.

HEI Code

Project Title

Funding Requested (€)m

Total Area (m²)

NUIG

Learning Commons

15

10,382

UCC

Cork University Business School (CUBS) Project

25

17,000

UCD

Future Campus Project

25

22,500

MU

Maynooth University Technology Society and Innovation Building

25

16,224

ITS

Extension to Central Campus (E01)

6.6

4,550

TCD

Law School

9

2,500

UL

Future Skills Academy

22.6

7,866

LIT

LIT City Centre Campus - Clare Street

0.7

1,243

ITC

New Information Science and Technology Bld.

13.05

6,000

LYIT

LYIT National Fire Safety Engineering Centre

1.87

563

GMIT

GMIT Cluain Mhuire Campus

3.5

7,330

TU Dublin

Design & Construct

7.5

6,176

ITT

IT Tralee Student Facilities Hub (SFH)

6.1

3,550

RCSI

Academic Healthcare Centre

3.4

2,900

DIAS

Astronomy, Space Science & Technology Study Centre - Dunsink Observatory

0.1

111