Schools Building Projects

Dáil Éireann Debate, Wednesday - 28 April 2021

Wednesday, 28 April 2021

Questions (549)

Duncan Smith

Question:

549. Deputy Duncan Smith asked the Minister for Education the status of the provision of a new primary school (details supplied) in County Kildare; and if she will make a statement on the matter. [21330/21]

View answer

Written answers

The major building project for the school referred to by the Deputy is included in my Department’s Construction Programme which is being delivered under the National Development Plan. The project is currently at an advanced stage of architectural planning - Stage 2(b) Detailed Design, which includes the application for statutory approvals and the preparation of tender documents. All statutory approvals have been secured.

The Stage 2(b) Report has been reviewed by my Department and Design Team confirmations, that they have carried out a final review of tender documentation have been received. 

The pre-qualification process to select a short list of contractors is currently nearing completion.

Upon completion of the pre-qualification process, my Department will revert to the school and its Design Team regarding the further progression of this major building project to the next stage of Architectural Planning, Stage 3 - Tender Stage.

Subject to no issues arising a tender stage normally takes between 6 to 8 months to complete. 