Dáil Éireann Debate, Tuesday - 11 May 2021

Tuesday, 11 May 2021

Questions (151)

Michael Fitzmaurice

Question:

151. Deputy Michael Fitzmaurice asked the Minister for the Environment, Climate and Communications the details of the progress made under the National Broadband Plan to date in terms of connections completed; if the programme is on track with its targets; if the programme remains within budget; if not, if costs have escalated; and if he will make a statement on the matter. [23999/21]

View answer

Written answers

The National Broadband Plan (NBP) State led Intervention will be delivered by National Broadband Ireland (NBI) under a contract to roll out a high speed and future proofed broadband network within the Intervention Area which covers 1.1 million people living and working in the over 544,000 premises, including almost 100,000 businesses and farms along with 695 schools. The deployment plan forecasts construction commenced in all counties within the first 2 years and over 90% of premises in the State having access to high speed broadband within the next four years. I am advised by NBI  that, as of 22 April 2021, over 207,000 premises across all counties have been surveyed which is ahead of schedule.  Nearly 4,000 premises have been passed with high speed broadband by the NBI network in Counties Cork and Cavan.

Further details are available on specific areas across the country through the NBI website which provides a facility for any premises within the intervention area to register their interest in being provided with deployment updates through its website www.nbi.ie. Individuals who register with this facility will receive regular updates on progress by NBI on delivering the network and specific updates related to their own premises as works commence. I am advised that NBI is working to provide more detail on its website, with a rolling update on network build plans. NBI also has a dedicated email address, reps@nbi.ie, which can be used by Oireachtas members for specific queries.

While substantial progress has been made to date, the Covid 19 pandemic has had an impact on the delivery of the fibre network resulting in delays on delivery of aspects of the programme. Impacts include challenges with mobilisation of key contractors with restrictions on operations, supply chain and logistic delays (both nationally and internationally), as well as the recruitment of key personnel as NBI and its contractors scale, up including challenges associated with on-boarding and training people. Inevitably, like many other organisations, NBI and contractor staff are at risk of contracting Covid 19 or may have to restrict their movements as a result of being a close contact posing further challenges. My Department has worked closely with NBI to put in place a remedial plan under the Contract to address the impacts of the Covid 19 pandemic on the project. There are no cost overruns associated with this project.

Broadband Connection Points (BCPs) are a key element of the NBP providing high speed broadband in every county in advance of the roll out of the fibre to the home network. As of 22 April, 304 BCP sites have been installed by NBI and the high speed broadband service will be switched on in these locations through service provider contracts managed by the Department of Rural and Community Development for publicly accessible sites and the Department of Education for schools. Further details can be found at https://nbi.ie/bcp-locations/.

My Department continues to work with the Department of Education to prioritise schools with no high speed broadband, within the Intervention Area, for connection over the term of the NBP. In this regard, an acceleration of this aspect of the National Broadband Plan was announced in December which will see some 679 primary schools connected to high speed broadband by 2022, well ahead of the original target delivery timeframe of 2026. Further details are available on the NBI website at https://nbi.ie/primary-schools-list/.