Skip to main content
Normal View

An Garda Síochána

Dáil Éireann Debate, Tuesday - 18 May 2021

Tuesday, 18 May 2021

Questions (333)

Pauline Tully

Question:

333. Deputy Pauline Tully asked the Minister for Public Expenditure and Reform when construction on a new Garda station in Bailieboro, County Cavan will commence; the estimated timeframe for completion; and if he will make a statement on the matter. [26523/21]

View answer

Written answers

The procurement phase for this project is well progressed with tenders currently being evaluated and it is expected that this phase will be completed shortly.  Following contract award, construction will take about 20 months to complete.

Top
Share