School Accommodation

Dáil Éireann Debate, Tuesday - 6 July 2021

Tuesday, 6 July 2021

Questions (300)

Martin Browne

Question:

300. Deputy Martin Browne asked the Minister for Education when refurbishment works on a school (details supplied) will be completed; and the estimated cost of this project. [36103/21]

View answer

Written answers

The project for the school referred to by the Deputy is part of the Cahir Amalgamation project. The brief for the project is the construction of a 16 classroom school with a two classroom Special Educational Needs Base. Construction works commenced in October 2020 and are progressing satisfactorily on site.

The cost of the works will be in excess of €8.5m. The original contract duration was 19 months however this is likely to increase due to the on-going Covid restrictions.