Harbours and Piers

Dáil Éireann Debate, Tuesday - 13 July 2021

Tuesday, 13 July 2021

Questions (638)

Holly Cairns

Question:

638. Deputy Holly Cairns asked the Minister for Agriculture, Food and the Marine the status of the upgrading of Dinish Pier, Castletownbere, County Cork; and when the upgrade is expected to be completed [38033/21]

View answer

Written answers

Essential Works Contract (Phase 1 of Completion) for the upgrading of Dinish Pier was awarded on 10th March 2021 to Sorensen Civil Engineering Ltd.  This is ongoing and on programme and is scheduled to be completed in August 2021.

 The Completion Works Tender (Phase 2) documents were issued to tender on 28th April 2021 and tenders were returned on 11th June 2021. A Tender Report is currently being prepared. It is expected that the Completion Works will commence in August 2021 and be substantially completed in March 2022.