Skip to main content
Normal View

National Broadband Plan

Dáil Éireann Debate, Tuesday - 28 September 2021

Tuesday, 28 September 2021

Questions (222)

Pádraig MacLochlainn

Question:

222. Deputy Pádraig Mac Lochlainn asked the Minister for the Environment, Climate and Communications if he will meet with a cross party delegation of county councillors and members of the Houses of the Oireachtas from County Donegal to discuss serious concerns regarding the current timeframe for delivering high speed fibre broadband under the National Broadband Plan to the thousands of homes still not connected in the county; and if his office will liaise with Donegal County Council to confirm such a meeting at the earliest opportunity. [46342/21]

View answer

Written answers

The National Broadband Plan (NBP) State led Intervention will be delivered by National Broadband Ireland (NBI) under a contract to roll out a high speed and future proofed broadband network within the Intervention Area which covers 1.1 million people living and working in the over 544,000 premises, including almost 100,000 businesses and farms along some 699 schools. The NBP roll out is currently a 7 year plan under the contract and deployment is due to be complete by the end of 2026. There are 32,734 premises in the Intervention Area in County Donegal that will receive access to high speed broadband under the National Broadband Plan. Government investment in Donegal in the NBP will be in the order of €128 million. I am advised by National Broadband Ireland that, as of 17 September, some 7,388 premises in County Donegal have been surveyed. Surveying is the first step towards delivering the new fibre network and informs design solutions for provision of the fibre network.

In addition to the challenges to the delivery of the NBP due to the Covid-19 pandemic, NBI has faced a range of other challenges due to the sheer scale and complexity of rolling out fibre to the home in a rural environment. These include significant tree trimming to ensure cable can be placed on overhead poles, remediation of ducting that has been in place for many decades, the co-ordination of hundreds of contracting crews and addressing the many issues arising week on week which could not have been foreseen until the build crews commenced work on the ground. My Department has worked closely with NBI to put in place a remedial plan under the Contract. This plan addresses delays experienced by NBI, primarily arising as a result of the Covid-19 pandemic, and re-baselines milestones for 2021. Work is underway to re-baseline milestones for 2022 and beyond.

While delivery of the Programme is the responsibility of NBI under the Contract, my Department continues to monitor delivery very closely in accordance with the Department’s role under the contract. In parallel with the ongoing oversight of the contract with NBI, the Department has also been working with the 31 Local Authorities, the County and City Management Agency (CCMA), the Roads Management Office (RMO), Broadband Officers and other Government Departments, where appropriate, to ensure that any possible barriers that might delay the rollout are addressed as soon as possible. This also includes engagement with other bodies such as Transport Infrastructure Ireland, Irish Rail and ComReg.

I also understand that NBI has had engagement with elected representatives from Donegal in relation to the roll out of the National Broadband Plan in recent months and I have asked NBI to ensure that this outreach continues. My officials and I are also available to meet with elected representatives in relation to matters falling under the remit of the Department.

Top
Share