Skip to main content
Normal View

Schools Building Projects

Dáil Éireann Debate, Thursday - 25 November 2021

Thursday, 25 November 2021

Questions (257)

Paul Murphy

Question:

257. Deputy Paul Murphy asked the Minister for Education the status of the planned timetable for the building of the new secondary school in Citywest, Dublin. [58132/21]

View answer

Written answers

The permanent school building project for the school referred to by the Deputy has been assigned to my Department’s Design & Build delivery programme. This delivery programme uses a professional external Project Manager to progress the project through the relevant stages of architectural planning, tender and construction.

The final grant of planning for the project was received in March 2021. My Department’s Project Manager together with their Design Team are engaged in the preparation of tender documentation for the project. Once this stage is complete, the project will then proceed to tender stage.

Top
Share