333. Deputy Pádraig Mac Lochlainn asked the Minister for Education the way her Department is progressing the new works at a school (details supplied). [58704/21]

View answer

Written answers

The school to which the Deputy refers was approved funding under my Additional Accommodation Scheme to build 2 mainstream classrooms, refurbishment of existing 2 classrooms, 2 SET rooms, Principal's Office, Staff Room/General Office, Store, and Staff/Disabled Shower WC. This project is devolved to the school authority for delivery.

I can confirm that my Department received a Stage 3 Tender Report from the school on the 19th November 2021. The report is currently being reviewed in the Department; the completion of this review is expected shortly and subsequent instruction will issue to the school authority in the coming days.