Schools Building Projects

Dáil Éireann Debate, Thursday - 16 December 2021

Thursday, 16 December 2021

Questions (381)

John Lahart

Question:

381. Deputy John Lahart asked the Minister for Education the status of the project at a school (details supplied) in terms of timelines and stages and the likely conclusion and opening dates. [62471/21]

View answer

Written answers

The Letter of Acceptance (LOA) issued to the preferred tenderer on the 29th July 2021 commencing the school building contract for the school referred to by the Deputy. 

The construction programme is 60 weeks with the new 16 classroom school expected to be completed in July 2022 and all external site works including the removal of current temporary accommodation to be completed by end September 2022.