Questions (72)

Paul McAuliffe

Question:

72. Deputy Paul McAuliffe asked the Minister for Transport when he expects the business case to be made for the metro north project by his Department; and if he will make a statement on the matter. [55827/21]

View answer

Written answers

The MetroLink project is currently at Decision Gate 1: Approval in Principle under the Public Spending Code.

The key document at Decision Gate 1 is the Preliminary Business Case and a draft Preliminary Business Case was submitted to my Department for initial review in line with the requirements of the Public Spending Code. I understand an updated Preliminary Business Case will be resubmitted very shortly and, subject to its compliance with the requirements of the Public Spending Code, I will then be in a position to seek Government approval for the project.

Approval at Decision Gate 1 will permit MetroLink enter the statutory planning system. At a project level I understand work is ongoing to complete all the necessary planning, environmental and property referencing documentation required for a planning application, with an expectation that this work will be completed by Q2 next year.