Housing Provision

Dáil Éireann Debate, Wednesday - 19 January 2022

Wednesday, 19 January 2022

Questions (445)

Rose Conway-Walsh

Question:

445. Deputy Rose Conway-Walsh asked the Minister for Housing, Local Government and Heritage the location of all built social housing provided in County Mayo in 2021; the location of the targeted 90 social homes by built in 2022; and if he will make a statement on the matter. [62935/21]

View answer

Written answers

A detailed Social Housing Construction Status Report (CSR) is published each quarter by my Department, which provides scheme level detail on new build social housing activity. The CSR provides details of the individual social housing new build projects, that make up the new build programme for each local authority, including Mayo. The most recent publication covers the period up to the end of Quarter 3 2021, and is available at the following link: www.gov.ie/en/publication/feea9-social-housing-construction-projects-status-report-q3-2021/.

In Mayo, the CSR for Q3 2021 shows there are 11 schemes consisting of 88 units onsite and there are a further 15 schemes of 225 units at various stages of design and procurement.

An excel version of this file can be downloaded at the following link:  data.gov.ie/dataset/social-housing-construction-status-report-q3-2021?package_type=dataset .