Schools Building Projects

Dáil Éireann Debate, Wednesday - 19 January 2022

Wednesday, 19 January 2022

Questions (805)

Seán Sherlock

Question:

805. Deputy Sean Sherlock asked the Minister for Education if she will address the matters raised in correspondence (details supplied); and the status of the project. [1610/22]

View answer

Written answers

The building project for Carrigtwohill campus will accommodate two primary schools and one post-primary school when complete and is being delivered under the Department’s Design and Build Programme. This delivery programme uses a professional external Project Management team to progress the project through the stages of architectural planning, tendering and construction.

On June 14th 2021, this campus project was included in a bundle of projects which were tendered to a newly established Design & Build Contractors Framework. The tenders were returned on October 27th 2021 and the tender assessment report from the Department's Project Manager has been recently received by the Department and is currently under review. It is anticipated that the Letter of Intent to appoint the Building Contractor will issue in the coming weeks in Quarter 1. Once a Contractor has been appointed, the Department will keep the school informed of the construction programme underpinning the contract.

With regard to the matter of road safety measures at the school's temporary site, the road network outside the school including traffic calming measures and pedestrian facilities are the responsibility of the relevant Local Authority. Local Authorities have the power to decide on road safety measures outside schools to ensure that measures are in place to protect the safety of local school children.