Defective Building Materials

Dáil Éireann Debate, Thursday - 27 January 2022

Thursday, 27 January 2022

Questions (204)

Dara Calleary

Question:

204. Deputy Dara Calleary asked the Minister for Housing, Local Government and Heritage further to Parliamentary Question Nos. 583, 584 and 585 of 19 January 2022, if he will provide a breakdown of the administrative cost headings for both local authorities; and if he will make a statement on the matter. [4107/22]

View answer

Written answers

Donegal and Mayo County Council have responsibility for the administration of the Defective Concrete Blocks Grant scheme. This includes the assessment of applications for eligibility and payment of grants to successful applicants under the specific remediation option approved.

Budget 2021 provided funding of €20 million to fund the operation of the Defective Concrete Blocks Grant scheme for the counties of Donegal and Mayo only. Details of the administrative costs of implementing the scheme in 2021 are outlined below.

Donegal

Salaries

€336,138.42

Computer Software Development, Equipment and Licensing

€25,764.66

Office Furniture/Equipment/Stationery/Communications

€305.84

Training

€465.00

Travel Expenses

€1,201.25

Total

€363,875.17

Mayo

Salaries

€49,388.69

Architects Fees

€82,784.50

Engineers Fees (review of files)

€33,531.30

QS Fees

€13,569.85

Appeals Costs

€14,760.00

Computer Software Development

€5,535.00

Petrographic Assessments

€799.50

Total

€200,368.84