Dáil Éireann Debate, Tuesday - 1 March 2022

Tuesday, 1 March 2022

Questions (444)

Paul Donnelly

Question:

444. Deputy Paul Donnelly asked the Minister for Defence the capital works that were carried out at Casement Aerodrome in 2021 and to date in 2022; and the estimated cost of each capital works project, in tabular form. [11233/22]

View answer

Written answers

As part of the Departments Infrastructure Development Plan the following capital works were at various stages of construction at Casement Aerodrome during 2021 and 2022:

Capital Project

Estimated Cost- Vat Inc

Watermains Upgrade

€1m

Upgrade of LED Runway Lighting

€0.4m

25M no danger area firing range and ancillary works

€0.353m

Hangar 5 Fire Detection and Suppression system

€0.260m

ISTAR Facility - Bldg 43

€0.214m

Hardstanding to take helicopter training platform

€0.210m

Replacement of Standby Generators

€0.2m

Hard Standing Breathing Apparatus House Fire Training Ground

€0.157m

The Deputy may also wish to note a Design Team was recently appointed in respect of the development of a new Military Medical Facility at Casement Aerodrome.