Question:469. Deputy Catherine Murphy asked the Minister for Education the estimated amount her Department has spent to date on the major refurbishment works being carried out at a school (details supplied). [17704/22]
View answerDáil Éireann Debate, Tuesday - 5 April 2022
469. Deputy Catherine Murphy asked the Minister for Education the estimated amount her Department has spent to date on the major refurbishment works being carried out at a school (details supplied). [17704/22]
View answerThe major new school construction project for the school referred to by the Deputy commenced on site in November 2021. Works are progressing satisfactorily with a contract duration of approximately 26 months.
The contract amount is in excess of €12.4m and expenditure to date is in accordance with the conditions of the contract.