Skip to main content
Normal View

Schools Refurbishment

Dáil Éireann Debate, Thursday - 5 May 2022

Thursday, 5 May 2022

Questions (185)

Violet-Anne Wynne

Question:

185. Deputy Violet-Anne Wynne asked the Minister for Education the estimated cost of the major refurbishment works being carried out at a school (details supplied); and when these works will be completed. [22456/22]

View answer

Written answers

The School referred to by the Deputy is part of a Schools Campus Project and the new school is currently at construction stage.  Works are progressing satisfactorily with a contract duration of approximately 36 months.

The contract amount for the Schools Campus Project is in excess of €24m and the expenditure to date is in accordance with the conditions of the contract.

Top
Share