886. Deputy Alan Kelly asked the Minister for Rural and Community Development the status of each individual project approved under the town and village renewal scheme in County Tipperary in each of the years of 2020 and 2021 including the grant approved for each project; and the completion date for each project. [22951/22]

View answer

Written answers

The Town and Village Renewal Scheme (TVRS) is part of a range of measures to support the revitalisation of rural Ireland. The programme is funded under Project Ireland 2040 as part of Our Rural Future.

In February 2022 I announced almost €18.5 million in funding for projects under the Town and Village Renewal Scheme 2021. I announced further funding of €850,000 in March for projects under the new Project Development Measure 2021.

Since the launch of the Scheme in 2016, over €113 million of funding has been approved for more than 1,400 projects across Ireland. I will shortly announce details of the 2022 Town & Village Renewal Scheme.

The following table outlines the details and status of each individual project approved under the Scheme in County Tipperary in each of the years of 2020 and 2021:

Scheme & Year

Town/Village

Amount Approved

Completion Date (As per Funding Agreement)

Current Project Status

TVRS 2020 Main Scheme

Birdhill

€22,500

31/08/2022

Project Complete

TVRS 2020 Main Scheme

Boherlahan Village

€171,000

31/08/2022

Project Ongoing

TVRS 2020 Main Scheme

Kilbarron

€51,525

31/08/2022

Project Ongoing

TVRS 2020 Main Scheme

Kilsheelan

€90,000

31/08/2022

Project Ongoing

TVRS 2020 Main Scheme

Loughmore Village

€200,000

31/08/2022

Project Ongoing

TVRS 2020 Main Scheme

Marlfield Village

€200,000

31/08/2022

Project Ongoing

TVRS 2020 Main Scheme

Templemore Town

€53,000

31/08/2022

Project Ongoing

TVRS 2020 Accelerated Measure Rd 1

Ballyporeen

€39,600.00

30/11/2020

Project Complete

TVRS 2020 Accelerated Measure Rd 1

Carrick On Suir

€25,000.00

30/11/2020

Project Complete

TVRS 2020 Accelerated Measure Rd 1

Thurles

€25,000.00

30/11/2020

Project Complete

TVRS 2020 Accelerated Measure Rd 1

Tipperary

€24,750.00

30/11/2020

Project Complete

TVRS 2020 Accelerated Measure Rd 2

Fethard

€22,500

30/11/2020

Project Complete

TVRS 2020 Accelerated Measure Rd 2

BCP's 8 Towns

€40,000

30/11/2020

Project Complete

TVRS 2020 Accelerated Measure Rd 2

Littleton

€25,000

30/11/2020

Project Complete

TVRS 2020 Accelerated Measure Rd 2

Nenagh

€25,000

30/11/2020

Project Complete

TVRS 2020 Accelerated Measure Rd 2

Terryglass

€24,784

30/11/2020

Project Complete

TVRS 2020 Accelerated Measure Rd 3

Ballingarry

€25,000.00

01/03/2021

Project Complete

TVRS 2020 Accelerated Measure Rd 3

Borrisokane

€36,000.00

01/03/2021

Project Complete

TVRS 2020 Accelerated Measure Rd 3

Cahir Inch Field

€40,000.00

01/03/2021

Project Complete

TVRS 2020 Accelerated Measure Rd 3

Clonmel

€40,000.00

01/03/2021

Project Complete

TVRS 2021 Main Scheme

Ballyporeen

€198,000

31/08/2023

Project Ongoing

TVRS 2021 Main Scheme

Carrick on Suir

€90,000

31/08/2023

Project Ongoing

TVRS 2021 Main Scheme

Tipperary Town

€500,000

31/08/2023

Project Ongoing

Top