Schools Building Projects

Dáil Éireann Debate, Tuesday - 14 June 2022

Tuesday, 14 June 2022

Questions (1040)

Eoin Ó Broin

Question:

1040. Deputy Eoin Ó Broin asked the Minister for Education the status of the new building for a school (details supplied); and the timelines for planning, tender, commencement and completion. [30471/22]

View answer

Written answers

The permanent building project for the school referred to by the Deputy is being delivered under my Department's Design and Build programme. This delivery programme uses a professional external Project Manager to progress the project through the relevant stages of architectural planning, tender and construction.

An application for planning permission for a 1,000 pupil post-primary school building, including a 4 classroom Special Educational Needs Unit, was submitted to the relevant Local Authority in June 2021. A Request for Further Information (RFI) was received on 27th July 2021 and the response submitted to the local authority on 7th December 2021. A Clarification of Further Information was received from the Local Authority on 12th January 2022 with the response submitted to the local authority on 24th January 2022.

The Grant of Planning decision was received from the Local Authority on 24th February 2022.

The next step in the progression of this project is the preparation of tender documentation. Once this stage is complete, the project will then proceed to tender stage.