Schools Building Projects

Dáil Éireann Debate, Tuesday - 26 July 2022

Tuesday, 26 July 2022

Questions (1111)

Róisín Shortall

Question:

1111. Deputy Róisín Shortall asked the Minister for Education the reason for the undue delay in approving essential works under the emergency programme for a school (details supplied) in Dublin 11, in view of the fact that the application was made in May 2022 and approval was not given until 19 July, which meant that it is too late for these emergency works to be completed over the summer holidays; if there is any way that this emergency work can be expedited; and if she will make a statement on the matter. [40950/22]

View answer

Written answers

I would like to inform the Deputy that the school to which she refers made two separate applications for funding on the 18th of May 2022, one for the removal of asbestos containing materials and one for a Universal Access project. Both projects required separate assessments from members of the Department’s Technical team.

Following the assessments, substantial savings were identified in the asbestos removal works and an increased scope of works was required in the universal access project to cater for a student with special needs who will be attending the school in 2024.

While the approval process took longer than normal the assessment process ensured that the scope of approved works was appropriate and fit for purpose.