asked the Minister for Local Government if he can give details of the amount of tourist road work completed in South West Cork on 30th September, 1964.
Ceisteanna—Questions. Oral Answers. - Cork Tourist Roads.
37.
As the reply is in the form of a tabular statement I propose, with your permission, a Cheann Comhairle, to circulate it with the Official Report.
Following is the statement:
APPROVED schemes under Tourist Road Grant, 1964-65, in South and West Cork.
Scheme |
Estimated Cost |
Amount Expended at 30th September, 1964 |
£ |
£ |
|
South Cork: |
||
Route T.29 between Carrigaphooka and Fairyland |
6,000 |
960 |
Route T.64 between Glebe and Rossmore |
6,000 |
5,940 |
West Cork: |
||
Route T.65 Bantry/Glengarriffe |
20,000 |
6,851 |
Route L.40 between Derragh and Togher |
9,000 |
5,644 |
Route L.61 Glengarriffe/Castletownbere at Coolieragh |
6,000 |
3,705 |
TOTALS |
47,000 |
23,100 |