Written Answers. - Town Traffic Congestion Relief.

364.

asked the Minister for the Environment the towns around the country which have currently provided detailed plans for the provision of a major trunk road by-pass which would relieve internal congestion within the towns affected and improve the travelling conditions along the major trunk roads.

Following is the information:

Town

Present Position

Carlow

Under construction. Scheduled for completion by 1979.

Clonakilty

Under construction. Scheduled for completion by 1979.

Letterkenny

Under construction. Completion expected during 1978.

Lifford

Under construction. Completion expected during 1979.

Limerick Southern Ring Road

Under construction. Completion expected by 1980.

Mallow

Under construction. Completion expected during 1978.

Monaghan

Under construction. Scheduled for completion in 1979.

Naas

Detailed plans approved. Construction is scheduled to commence in mid 1979. Completion is expected by 1982.

Navan

Under construction. Scheduled for completion in 1982.

New Ross

Under construction. Completion expected during 1978.

Roscommon

Under construction. Scheduled for completion in 1980.

Tallaght

Under construction. Part of the by-pass has been completed. Final completion expected by 1980.

Tullamore

Under construction. Scheduled for completion in 1980.

I understand that outline proposals on preliminary reports have been prepared in respect of a number of other such places.