Written Answers. - Castleknock (Dublin) School.

698.

asked the Minister for Education if he will confirm his commitment to provide a post-primary school in Castleknock, County Dublin within three years; if he will outline in detail the stages that have to be gone through before the school is built and opened; if he will list the deadlines for each of these stages and the date of the opening of the school; and if he will make a statement on the matter.

It is intended that the new post-primary school proposed for Castleknock will be provided by September 1985. Consultants for the project will be appointed within the next few weeks. The stages then required for the completion of the project are (1) Architectural planning, 12 months (approx); (2) Seeking of tenders and awarding of contract, 2-3 months; (3) Construction period completion and handover, 15-18 months.