Alan M. Dukes
Ceist:88 Mr. Dukes asked the Minister for Defence the works it is proposed to carry out in Army Barracks in 2002; the cost of same; and when such works will be commenced and completed in each case. [4790/02]
Vol. 548 No. 3
88 Mr. Dukes asked the Minister for Defence the works it is proposed to carry out in Army Barracks in 2002; the cost of same; and when such works will be commenced and completed in each case. [4790/02]
122 Mr. Shatter asked the Minister for Defence the works it is proposed to carry out in Army Barracks in 2002; the cost of same; and when such works will be commenced and completed in each case. [4871/02]
I propose to take Questions Nos. 88 and 122 together.
I have set out details of the proposed capital building programme for 2002 in the form of a tabular statement, and it will be circulated in the Official Report. It will be appreciated that the costs, start and completion dates are target figures and subject to change depending on circumstances.
Building Programme – 2002 (Army Barracks)
Description |
Location |
Cost(Euro) |
DurationMonths |
Start date2002 |
Finish Date2002 |
Finish Date2003 |
Female Ablution Block |
Bere Island |
150,000.00 |
6.00 |
June |
December |
|
Upgrade Runways |
Casement |
8,100,000.00 |
5.00 |
June |
November |
|
Upgrade Boiler InstallationHanger – 3 |
Casement |
150,000.00 |
4.00 |
June |
October |
|
Upgrade Accommodation Blocks |
Cathal Brugha Bks. |
2,400,000.00 |
8.00 |
August |
April |
|
Upgrade Other Ranks Accommodation |
Clonmel Bks. |
150,000.00 |
6.00 |
June |
December |
|
Upgrade Officers Mess Kitchen |
Collins, Cork |
400,000.00 |
6.00 |
August |
February |
|
Fire Upgrade Accommodation Blocks |
Columb Bks. |
130,000.00 |
3.00 |
November |
February |
|
Upgrade Bilets – Phase 3 |
Coolmoney Camp |
760,000.00 |
6.00 |
June |
December |
|
Ablution Blocks – Phase 3 |
Coolmoney Camp |
380,000.00 |
4.00 |
June |
October |
Description |
Location |
Cost(Euro) |
DurationMonths |
Start date2002 |
Finish Date2002 |
Finish Date2003 |
Upgrade – Civil WorksPhase 1 |
Coolmoney Camp |
1,525,000.00 |
5.00 |
September |
February |
|
Combined Vehicle Workshops |
Curragh Camp |
9,070,600.00 |
11.00 |
January |
December |
|
Refurbish Old Riding School |
Curragh Camp |
100,000.00 |
3.00 |
April |
July |
|
Sewage System Upgrade |
Curragh Camp |
1,270,000.00 |
6.00 |
November |
May |
|
Vehicle Spray Booth |
Curragh Camp |
70,000.00 |
2.00 |
June |
August |
|
Upgrade Privates Mess |
Finner Camp |
200,000.00 |
4.00 |
October |
February |
|
Upgrade Sewage Treatment Plant |
Kilbride Camp |
130,000.00 |
5.00 |
August |
January |
|
Upgrade Production Well |
Kilworth Camp |
65,000.00 |
2.00 |
April |
June |
|
Civil Works UpgradePhase 1 |
Kilworth Camp |
425,000.00 |
12.00 |
May |
May |
|
New Ablution Block |
Kilworth Camp |
190,000.00 |
5.00 |
June |
November |
|
Upgrade Accommodation Block |
McKee Bks. |
2,800,000.00 |
10.00 |
October |
August |
|
Deceased DF Members Memorial |
McKee Bks. |
130,000.00 |
3.00 |
August |
November |
|
Upgrade Accommodation – Phase 1 |
Naval Base |
650,000.00 |
6.00 |
October |
April |
|
New Cookhouse and Dining Hall |
Renmore Bks. |
4,100,000.00 |
11.00 |
October |
September |
|
Upgrade Accommodation Block |
Sarsfield Bks. |
1,000,000.00 |
12.00 |
September |
September |
|
External Lighting |
Sarsfield Bks. |
76,000.00 |
3.00 |
May |
August |
|
Alarms Upgrade – Electrical and Fire |
St. Bricín's Hospital |
600,000.00 |
4.00 |
August |
December |