181 Mr. Coveney asked the Minister for Education and Science if he will give a detailed reason for the delay with proceeding with the promised new primary school in Ballygarvan, County Cork; the funding that has been committed to this project; and when he expects it to proceed. [4076/04]

Amharc ar fhreagra

Freagraí scríofa

The property management section of the Office of Public Works, which acts on behalf of my Department for site acquisitions, is exploring the possibility of acquiring a site for the provision of new primary school in Ballygarvan, County Cork. Due to the commercial sensitivities associated with site acquisition, I am unable to provide detailed information relating to specific site purchases.

With regard to the delivery of a new school building, when publishing the 2004 school building programme I outlined that my strategy going forward will be grounded in capital investment based on multi-annual allocations. My officials are reviewing all projects which were not authorised to proceed to construction as part of the 2004 school building programme, with a view to including them as part of a multi-annual school building programme from 2005. I expect to be in a position to make further announcements on this matter in the course of the year.