An annualised schedule of developments in the provision of a new Garda Station at Leixlip is as follows: 2000, procurement phase of a development site; 2001, procurement phase of a development site; 2002, procurement of development site finalised; 2003, design team appointment — sketch scheme drawn up; and 2004, revised brief received from the Garda Síochána — revised sketch scheme in preparation.
The provision of a new station facility will be contingent on the receipt of design approval, planning permission and a funding provision. At present the Garda station at Leixlip is placed at No. 17 on the priority list for the Garda building programme.