Schools Building Projects

Dáil Éireann Debate, Thursday - 6 May 2010

Thursday, 6 May 2010

Ceisteanna (158, 159)

Dinny McGinley

Ceist:

157 Deputy Dinny McGinley asked the Tánaiste and Minister for Education and Skills the number and names of all primary schools in County Donegal that have applied for extensions, refurbishment or renovation grants; and if she will make a statement on the matter. [18502/10]

Amharc ar fhreagra

Freagraí scríofa

Information in respect of the current school building programme along with all assessed applications for major capital works, including the Co. Donegal projects referred to by the Deputy, is now available on my Department's website at www.education.ie.

The priority attaching to individual projects is determined by published prioritisation criteria, which were formulated following consultation with the Education Partners. There are four band ratings under these criteria, each of which describes the extent of accommodation required and the urgency attaching to it. Band 1 is the highest priority rating and Band 4 is the lowest. Documents explaining the band rating system are also available on my Department's website.

For the Deputy's convenience, a list of 46 applications from Co. Donegal primary schools currently seeking major capital works building projects is set out for ease of reference.

County

School Roll No.

School Name

Current Status

Application For

Provisional Band Rating

Donegal

01733B

Ardara Mixed N S Ardara (Donegal)

Application

Extension/Refurb

Band 3

Donegal

03294L

S N Caiseal Na Gcorr Gort A Choirce (Donegal)

Application

Extension/Refurb

Band 3

Donegal

04809A

Scoil An Aingil Choimheadai An Cheididh (Donegal)

Application

Extension/Refurb

Band 2

Donegal

09009Q

Rockfield Ns, Ballyshannon, (Donegal)

Application

Extension/Refurb

Band 4

Donegal

11843O

S N Neill Mor Killybegs (Donegal)

Application

Extension/Refurb

Band 1

Donegal

12077E

Scoil Naomh Fiachra Letterkenny (Donegal)

Application

Extension/Refurb

Band 1

Donegal

15770K

S N Naomh Naille Na Caologa (Donegal)

Application

Extension/Refurb

Band 3

Donegal

16138S

Raphoe Central N S Raphoe (Donegal)

Application

Extension/Refurb

Band 3

Donegal

16608G

Killybegs Common N S The Commons (Donegal)

Application

Extension/Refurb

Band 3

Donegal

16819T

S N Gort An Choirce Leitir Ceanainn (Donegal)

Application

New School

Band 2

Donegal

16821G

Clochar Padraig Naofa Carndonagh (Donegal)

Application

Extension/Refurb

Band 2

Donegal

16837V

S N Duchoraidh Duchoraidh (Donegal)

Application

Extension/Refurb

Band 3

Donegal

16850N

St Garvan’S N.S. Drum Halla (Donegal)

Application

Extension/Refurb

Band 3

Donegal

17040G

Sn Naomh Samhthann Drumdoit (Donegal)

Application

Extension/Refurb

Band 3

Donegal

17057A

Dromcaoin Bealach Fheid Dromcaoin (Donegal)

Application

Extension/Refurb

Band 3

Donegal

17241Q

S N Domhnach Mor Castlefin (Donegal)

Application

Extension/Refurb

Band 2

Donegal

17260U

Scoil An Leinbh Iosa Killymard (Donegal)

Application

Extension/Refurb

Band 2

Donegal

17721H

Scoil Treasa Naofa Malainn (Donegal)

Application

Extension/Refurb

Band 3

Donegal

17828C

Scoil Adhamhnain Rathbhoth (Donegal)

Application

Extension/Refurb

Band 2

Donegal

17945G

Scoil Naomh Chaitriona, Ballyshannon

Awaiting Appointment of Design Team

New School

Band 2

Donegal

18058H

Scoil Naomh Seosamh Rathdomhnaill (Donegal)

Application

Extension/Refurb

Band 3

Donegal

18129E

Scoil Naomh Peadar (Donegal)

Application

Extension/Refurb

Band 2

Donegal

18131O

S N Muire Gan Smal Ard Aratha (Donegal)

Application

Extension/Refurb

Band 2

Donegal

18251B

Ayr Hill N S Ramelton Ramelton (Donegal)

Application

Extension/Refurb

Band 2

Donegal

18286U

S N Na Hacrai Ailt An Chorrain (Donegal)

Application

Extension/Refurb

Band 3

Donegal

18371L

Scoil Mhuire An Craosloch (Donegal)

Application

Extension/Refurb

Band 2

County

School Roll No.

School Name

Current Status

Application For

Provisional Band Rating

Donegal

18520C

Scoil Phadraig Rath Seinche (Donegal)

Application

Extension/Refurb

Band 2

Donegal

18605K

Scoil Naomh Padraig Boys Carndonagh (Donegal)

Application

Extension/Refurb

Band 2

Donegal

18625Q

Scoil Colmcille, Convent Road, Letterkenny

Awaiting Appointment of Design Team

Extension/Refurb

Band 1

Donegal

18737E

Scoil Bhride, Conmhagh, Lifford, (Donegal)

Application

Extension/Refurb

Band 2

Donegal

19009W

Craanford N S Craanford (Donegal)

Application

Extension/Refurb

Band 3

Donegal

19228L

S N Naomh Brid Na Dunaibh (Donegal)

Application

Extension/Refurb

Band 3

Donegal

19310T

Scoil Naomh Earnan (Donegal)

Application

Extension/Refurb

Band 2

Donegal

19313C

Glenswilly National School, Newmills, Letterkenny

Awaiting Appointment of Design Team

Extension/Refurb

Band 1

Donegal

19518U

S N Naomh Baoithin Sc Naomh Baoithin (Donegal)

Application

Extension/Refurb

Band 2

Donegal

19686S

St Macartans Central Bundoran (Donegal)

Application

Extension/Refurb

Band 3

Donegal

19927O

Scoil Mhuire B & C, Stranorlar

Awaiting Appointment of Design Team

New School

Band 1

Donegal

19959E

Scoil Naomh Fionan Whitecastle (Donegal)

Application

Extension/Refurb

Band 2

Donegal

19967D

Scoil Iosagain, Buncrana

Awaiting Appointment of Design Team

Extension/Refurb

Band 1

Donegal

20096E

Gaelscoil Na Gceithre Maistri Baile Dun Na Ngall (Donegal)

Application

New School

Band 2

Donegal

20097G

Gaelscoil Bhun Crannach Bun Crannach (Donegal)

Application

New School

Band 2

Projects in Architectural Planning

Donegal

16672P

St. Patricks Primary School, Lurgybrack, Co. Donegal.

In advanced Architectural Planning

1.1

Extension/Refurbishment

Donegal

18052S

Scoil Mhuire gan Smal, Letterkenny, Co. Donegal.

In advanced Architectural Planning

1.1

Extension/Refurbishment

Donegal

18219F

SN Chonaill, Machaire Chlochair, Bun Beag, Co. Dhun na nGall

In advanced Architectural Planning

2.1

Extension/Refurbishment

Donegal

19971R

Gaelscoil Adhamhnain, Letterkenny, Co. Donegal.

In advanced Architectural Planning

1.1

Extension/Refurbishment

Donegal

20150H

Holy Family NS, Ballyshannon, Donegal

In advanced Architectural Planning

1.4

Extension/Refurbishment

Dan Neville

Ceist:

158 Deputy Dan Neville asked the Tánaiste and Minister for Education and Skills if she will provide funding in 2010 for the completion of a new school (details supplied) in County Limerick; and if she will make a statement on the matter. [18509/10]

Amharc ar fhreagra

I can confirm that the school to which the Deputy refers has made an application to my Department for large scale capital funding. The application has been assessed in accordance with the published prioritisation criteria for large scale building projects and assigned a band 2.2 rating, reflecting the fact that the deficit in mainstream accommodation represents a significant proportion of the school's overall needs.

Information in respect of the current school building programme, along with all assessed applications for major capital works, including the project referred to by the Deputy, is now available on my Department's website at www.education.ie.

The priority attaching to individual projects is determined by published prioritisation criteria, which were formulated following consultation with the Education Partners. There are four band ratings under these criteria, each of which describes the extent of accommodation required and the urgency attaching to it. Band 1 is the highest priority rating and Band 4 is the lowest. Documents explaining the band rating system are also available on my Department's website.

The progression of all large scale building projects, including this project, from initial design stage through to construction phase will be considered in the context of my Department's multi-annual School Building and Modernisation Programme. The Department is considering the most effective way of delivering this project, including examining the feasibility of allowing it to proceed as a Public Private Partnership project.

However, in light of current competing demands on the capital budget of the Department, it is not possible to give an indicative timeframe for the progression of the project at this time.

Question No. 159 answered with Question No. 24.