Schools Building Projects

Dáil Éireann Debate, Wednesday - 6 June 2012

Wednesday, 6 June 2012

Ceisteanna (202, 203, 204)

Éamon Ó Cuív

Ceist:

188 Deputy Éamon Ó Cuív asked the Minister for Education and Skills the number of second level school projects that are in Band 2:1 that have completed stage 2B and are not in the five year building programme announced this year; the estimated gross cost of these projects; the names and roll numbers of the schools involved; and if he will make a statement on the matter. [26915/12]

Amharc ar fhreagra

Éamon Ó Cuív

Ceist:

189 Deputy Éamon Ó Cuív asked the Minister for Education and Skills the number of first level or primary school projects that are in Band 2:1 and that have completed stage 2B and are not in the five year programme announced this year; the gross estimated cost of these projects; the names and roll numbers of the schools involved; and if he will make a statement on the matter. [26916/12]

Amharc ar fhreagra

Éamon Ó Cuív

Ceist:

190 Deputy Éamon Ó Cuív asked the Minister for Education and Skills the number of primary school projects that are in Band 2:1 and are at stage 2B at present and are not included in the five year building programme announced this year; the estimated gross cost of these projects; the names and roll numbers of the schools involved; and if he will make a statement on the matter. [26917/12]

Amharc ar fhreagra

Freagraí scríofa

I propose to take Questions Nos. 188 to 190, inclusive, together.

There are no second level schools that are in Band 2.1, that have completed stage 2(b) and that are not in the five year construction programme. There are, however, three such second level projects which are currently working toward the completion of stage 2(b). These are Colaiste Abbain, Wexford, RN71600B, St. Brendan's College, Bray, RN61790D and Scoil Phobail, Clifden, RN91412M. Taken together these three second level projects have an estimated gross cost of twenty million euro.

There are no primary schools with a band rating of 2.1, that have completed stage 2(b) and that are not in the five year construction programme. There are five such primary school projects which are currently working toward the completion of stage 2(b). These are St. Marys NS, Bagnalstown, Co Carlow, RN11135K; Scoil Odhran Naofa, Mullingar, Co Westmeath, RN17932U; Scoil Tigh an Iubhair, Co Louth, RN18635T; Scoil Naomh Padraig, Baconstown, Co Meath, RN02905J andSt Marys Central NS, Donnybrook, Dublin 4, RN19727G. The estimated gross cost of these five primary school projects is seven million euro.