Schools Building Projects Status

Dáil Éireann Debate, Tuesday - 13 November 2012

Tuesday, 13 November 2012

Ceisteanna (274)

Michael Creed

Ceist:

274. Deputy Michael Creed asked the Minister for Education and Skills if he will provide an update regarding the progress at design stage for a new school (details provided) in County Cork; when he expects to be in a position to move this project to planning application stage; and if he will make a statement on the matter. [49681/12]

Amharc ar fhreagra

Freagraí scríofa

The major building project for the school referred to by the Deputy is at Stage 2(a) Developed Sketch Design. The stage 2(a) submission is currently with my Department for consideration. Once the stage 2(a) is approved the project will progress to stage 2(b) which includes applications for planning permission, Fire Safety Certification, Disability Access Certification and the preparation of tender documents.

Due to competing demands on my Department's capital budget, imposed by the need to prioritise the limited funding available for the provision of additional school accommodation to meet increasing demographic requirements, it was not possible to include the project referred to by the Deputy in the five year construction programme.

Schools which have not been included in the five year construction programme, but which were announced for initial inclusion in the building programme will continue to be progressed to final planning stages in anticipation of the possibility of further funds being available to my Department in future years. The project referred to by the Deputy remains available to be considered for progression in that context.