Schools Building Projects Status

Dáil Éireann Debate, Wednesday - 2 July 2014

Wednesday, 2 July 2014

Ceisteanna (76)

Dan Neville

Ceist:

76. Deputy Dan Neville asked the Minister for Education and Skills the position regarding an extension to a school building (details supplied) in County Limerick. [28628/14]

Amharc ar fhreagra

Freagraí scríofa

The delivery of the school extension referred to by the Deputy has been devolved to Limerick and Clare Education and Training Board (ETB).

The Design Team appointed by the ETB are currently finalising the Stage 2a submission (Developed Sketch Design). When complete, approval will be given to the ETB to proceed to Stage 2b (Detailed Design), which involves obtaining planning permission, fire certificate and disability access certificate and the completion of tender documents.