The major building project for the school to which the Deputy refers is at an advanced stage of architectural planning, Stage 2(b) - Detailed Design, which includes the applications for Planning Permission, Fire Certificate and Disability Access Certificate and the preparation of Tender Documents. All statutory approvals have been secured and the Design Team have been authorised to complete Stage 2(b).