Swimming Pool Programme Status

Dáil Éireann Debate, Tuesday - 18 October 2016

Tuesday, 18 October 2016

Ceisteanna (620)

John Curran

Ceist:

620. Deputy John Curran asked the Minister for Transport, Tourism and Sport when his Department plans to give South Dublin County Council written approval to move to stage 3 of the Lucan swimming pool project; and if he will make a statement on the matter. [30231/16]

Amharc ar fhreagra

Freagraí scríofa

The Local Authority Swimming Pool Programme (LASPP) provides for grant aid to local authorities towards the capital costs of new swimming pools or the refurbishment of existing pools.  There are four stages in the development of a project under the Local Authority Swimmimg Pool Programme, namely Preliminary Report, Contract Documents, Tender and Construction.

In January of this year, my Department contacted local authorities and sought expressions of interest in a limited round of swimming pool allocations. There were three expressions of interest received for new pools, two of which were valid and both in Dublin.  Having assessed existing commitments and the funding available, it was decided to include the proposal from South Dublin County Council (SDCC) for a new swimming pool in Lucan in the LASPP.

My Department wrote to SDCC in April 2016 advising the Council to undertake the Preliminary Report stage which includes the Feasibility Study, Appointment of Consultants for Preliminary Proposals and Design Brief.  Documentation in this regard was received from SDCC in July and is currently under examination by my Department's technical advisor and my officials. In this regard, I have asked that this project would be prioritised in order to progress it to the next stage in the programme, i.e. the Contract Documents stage, as soon as possible.