Schools Building Projects Status

Dáil Éireann Debate, Thursday - 6 April 2017

Thursday, 6 April 2017

Ceisteanna (124)

Seán Fleming

Ceist:

124. Deputy Sean Fleming asked the Minister for Education and Skills the position regarding a new school building (details supplied); and if he will make a statement on the matter. [17153/17]

Amharc ar fhreagra

Freagraí scríofa

The major building project for the school to which the Deputy refers is an advanced stage of architectural planning - Stage 2(b) - Detailed Design, which includes the applications for Planning Permission, Fire Certificate and Disability Access Certificate and the preparation of Tender Documents. All applications for Statutory Approvals have been lodged and the Disability Access Certificate has been secured.

The Department and its design team are currently engaged with the Local Authority regarding the planning application, including dealing with a Request for Further Information.

When all Statutory Approvals are secured the Design Team will finalise the Stage 2(b) - Detailed Design submission which will be submitted to the Department for review. Following receipt and consideration of that report my Department will revert to the school with regard to the further progression of the project at that time.