Schools Building Projects Status

Dáil Éireann Debate, Wednesday - 11 October 2017

Wednesday, 11 October 2017

Ceisteanna (102)

Donnchadh Ó Laoghaire

Ceist:

102. Deputy Donnchadh Ó Laoghaire asked the Minister for Education and Skills the status of a school (details supplied). [43130/17]

Amharc ar fhreagra

Freagraí scríofa

The Design Team for this project has commenced the Pre-qualification process and the closing date for the e-tenders advertisement was the 6th October 2017.  The Pre-qualification of contractors involves the compiling of a shortlist of contractors to ensure that there are a number of appropriate and suitable candidates who can undertake the works successfully.  This process when commenced normally takes between 8 and 12 weeks to complete. The invitation to tender will issue to the shortlist of contractors when the pre-qualification process is complete. The anticipated construction period is 18 months as outlined in the pre-qualification notice.