Amharc ar fhreagraThe Design Team for this project has commenced the Pre-qualification process and the closing date for the e-tenders advertisement was the 6th October 2017. The Pre-qualification of contractors involves the compiling of a shortlist of contractors to ensure that there are a number of appropriate and suitable candidates who can undertake the works successfully. This process when commenced normally takes between 8 and 12 weeks to complete. The invitation to tender will issue to the shortlist of contractors when the pre-qualification process is complete. The anticipated construction period is 18 months as outlined in the pre-qualification notice.