The major building project referred to by the Deputy is at an advanced stage of architectural planning - Stage 2(b), which includes the applications for Planning Permission, Fire Certificate and Disability Access Certificate and the preparation of Tender Documents. All statutory applications have been secured.
The Brief Change Request for the project was received by my Department. However, on initial review it was found that the documents submitted were incomplete and further information was requested and is awaited from the School and its Design Team.
When these outstanding documents are received and reviewed and a determination has been made on the Brief Change Request, the Design Team will be in a position to finalise the Stage 2(b) Report. Upon receipt and review of this report my Department will revert to the school with regard to the further progression of the project at that time.