As the Deputy may be aware, the project to which she refers has been devolved for delivery to the local Education and Training Board (LMETB).
The project has been delayed mainly due to design issues. Having tendered for the project, the need for additional security features for the proposed building became apparent. These required a change in brief with the consequent design alterations. The project is currently at stage 2 B of the architectural planning process and a revised stage 2 B cost plan, to include the additional works, was recently submitted to my Department for consideration.
To date €244,841 has been spent on Design Team Fees, Planning fees, DAC fees and surveys for the project.
My Department is currently reviewing its programme for capital expenditure in 2018 and 2019. The progression of building projects, including the new HQ for LMETB, will be considered in that context.