374. Deputy Billy Kelleher asked the Minister for Health the primary care centre projects announced on 17 July 2012, in tabular form; the status of each; and if he will make a statement on the matter. [8527/18]

Amharc ar fhreagra

Freagraí scríofa

Delivery of primary care infrastructure is a dynamic process, which evolves to take account of changing circumstances including the feasibility of implementation.

The table below gives details of the 35 locations announced on 17 July 2012, and their current status including estimated opening dates. Five of these primary care centres are already operational and eleven are projected to open by the end 2018.

In addition, it should be noted that 67 primary care centres have been opened since 2011, and a further 6 primary care centres are projected to open in 2018, in addition to those shown in the table below.

Count

HSE Region

County

Location / PCT Name

Delivery Method

Project Status - Q4 2017

1

DML

Dublin

Rowlagh / North Clondalkin

Direct build

Stage 2a design team report completed. Purchase agreement finalised with adjoining school, subject to planning permission being granted for the development. HSE awaiting letter from Dept of Education in order to submit planning application.

2

DML

Dublin

Curlew Road / Crumlin / Drimnagh

Direct build

Planning permission in place. Options being reviewed following reconfiguration of services in the area.

3

DML

Dublin

Knocklyon / Rathfarnham

Direct build

Planning permission in place. Purchase of site being progressed.

4

DML

Wicklow

Rathdrum

Operational Lease

Planning approved for retrofit of existing building, but now needs new building. Discussions ongoing with developer.

5

DML

Kildare

Kilcock

PPP

Construction complete. Projected opening Q1 2018

6

DNE

Dublin

Coolock / Darndale

PPP

Construction nearing completion. Projected opening Q2 2018

7

DNE

Dublin

Summerhill, north inner city Dublin

PPP

In construction. Projected opening Q3 2018

8

DNE

Dublin

Balbriggan

Operational Lease

Operational since Q3 2017

9

DNE

Dublin

Swords

Operational Lease

Preferred bidder selected. Letter of Intent issued August 2017.

10

DNE

Louth

Drogheda north

Operational Lease

Existing building requires fitout. Projected completion Q1 2018 and operational Q2 2018.

11

DNE

Meath

Laytown and Bettystown

Operational Lease

Re-advertised in November 2017. Submissions received, currently under review.

12

DNE

Meath

Kells

Operational Lease

Operational since Q1 2016

13

DNE

Monaghan

Carrickmacross

Operational Lease

Layouts agreed. Finalising Agreement for Lease.

14

South

Carlow

Tullow / Rathvilly / Hacketstown

Direct build

Adjoining landowner has re-engaged with HSE. Options being reviewed.

15

South

Kilkenny

Kilkenny city (East)

Operational Lease

Letter of Intent issued. Layouts being reviewed. Legal discussions progressing.

16

South

Wexford

Wexford town

PPP

In Construction. Projected opening Q2-Q3 2018

17

South

Waterford

Dungarvan

PPP

In Construction. Projected opening Q2-Q3 2018

18

South

Waterford

Waterford city (east)

PPP

In Construction. Projected opening Q2-Q3 2018

19

South

Cork

Cork city - Ballyphehane / Togher / Greenmount / The Lough

Operational Lease

Letter of Intent issued. Layouts being developed. Planning in discussion with local authority.

20

South

Kerry

Tralee

Operational Lease

Letter of Intent issued. Layouts being reviewed. Planning permission received.

21

South

Tipperary

Carrick-on-Suir

PPP

In Construction. Projected opening Q2 2018

22

South

Tipperary

Clonmel

Operational Lease

Reviewing accommodation requirements before progressing to stage 3. Existing HSE facilities being reviewed.

23

West

Tipperary

Thurles

Operational Lease

Letter of Intent issued. Agreement for Lease signed. Planning application submitted.

24

West

Limerick

Limerick city (Ballinacurra / Weston)

PPP

Operational Q1 2018

25

West

Clare

Ennis

Operational Lease

Stage 3 priced offers being evaluated.

26

West

Galway

Tuam

PPP

Operational since Q4 2017.

27

West

Galway

Gort

Operational Lease

Letter of Intent withdrawn 24/05/2016. Possible re-advertisement.

28

West

Roscommon

Boyle

PPP

Operational Q1 2018

29

West

Roscommon

Ballaghadereen

Operational Lease

Letter of Intent issued 27/10/2015. Project progressing to Agreement for Lease.

30

West

Mayo

Westport

PPP

In Construction. Projected opening Q2 2018

31

West

Mayo

Claremorris

PPP

Construction complete. Projected opening Q1 2018

32

West

Sligo

Ballymote

PPP

Construction complete. Projected opening Q1 2018

33

West

Donegal

An Clochán Liath - Dungloe

Operational Lease

Re-advertised for Operational Lease option. Expressions of interest received. Stage 2 responses received, preparing to issue stage 3 letters.

34

West

Donegal

Donegal town

Operational Lease

Expressions of interest received. Currently being reviewed

* Coolock and Darndale were announced as two separate locations