The number of eVDSL premises passed by eir under the terms of the April 2017 Commitment Agreement for the three Quarters referenced by the Deputy is set out below:
Quarter 2 2017: 0 premises
Quarter 3 2017: 2,918 premises
Quarter 4 2017: 392 premises
Premises passed will now be able to avail of eVDSL enabled services which include speeds from 30Mbps up to and including 100Mbps. Information on eir's planned rural deployment is available at
http://fibrerollout.ie/eircode-lookup. Quarterly updates on eir's rural deployment are published on this website. Of the 300K planned rural deployment, my Department has verified that eir has passed a total of 121,000 premises as at Quarter 4 2017.
A copy of the Commitment Agreement is available on my Department’s website www.dccae.gov.ie.