142. Deputy James Browne asked the Minister for Public Expenditure and Reform when works will commence for the non-coastal flood relief works at Wexford Racecourse; and if he will make a statement on the matter. [12452/18]

Amharc ar fhreagra

Freagraí scríofa

I have been advised that the Office of Public Works approved funding of €126,000 in February 2018 under its Minor Flood Mitigation Works and Coastal Protection scheme to Wexford County Council for flood relief works at Wexford Racecourse, Co Wexford.

The implementation of these works is a matter for the Council and I understand that following the planning process and procurement of a contractor it is expected that works will commence in Q3 of 2018.