Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Schools Building Projects Data

Dáil Éireann Debate, Thursday - 22 March 2018

Thursday, 22 March 2018

Ceisteanna (89)

Joan Burton

Ceist:

89. Deputy Joan Burton asked the Minister for Education and Skills if the revised stage 2 (b) report for a school (details supplied) has been received in his Department; if the project can now proceed to tender stage; and if he will make a statement on the matter. [13477/18]

Amharc ar fhreagra

Freagraí scríofa

The building project referred to by the Deputy is for a new 24 classroom school including a Special Needs Unit, with a floor area of approx. 4,748m2.

The project is currently at Stage 2B of Architectural Planning - Detailed Design Stage, which includes applications for all statutory consents, including Planning Permission, Disability Access Certificate and Fire Safety Certificate and also the preparation of tender documentation. Planning Permission for this project was received in August 2017.

 The Stage 2B report has been received by my Department, the review is complete, with some minor issues to be addressed by the Design Team.

Barr
Roinn