Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Schools Building Projects Status

Dáil Éireann Debate, Tuesday - 17 April 2018

Tuesday, 17 April 2018

Ceisteanna (369)

Frank O'Rourke

Ceist:

369. Deputy Frank O'Rourke asked the Minister for Education and Skills the timeline for the commencement of building works for a school (details supplied); the anticipated completion date; and if he will make a statement on the matter. [15480/18]

Amharc ar fhreagra

Freagraí scríofa

The major building project referred to by the Deputy is at an advanced stage of architectural planning Stage 2b (Detailed Design), which includes the application for statutory approvals and the preparation of tender documents. All statutory approvals have been secured.

The Stage 2(b) submission has been reviewed by my Department and a letter recently issued to the school and its Design Team advising them of a timeframe for the progression of this project. This project has been authorised to commence the Pre-Qualification of Contractors.

Barr
Roinn