Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Social and Affordable Housing Data

Dáil Éireann Debate, Thursday - 21 June 2018

Thursday, 21 June 2018

Ceisteanna (254)

John Curran

Ceist:

254. Deputy John Curran asked the Minister for Housing, Planning and Local Government the number of social housing completions by each local authority in 2017; and if he will make a statement on the matter. [27185/18]

Amharc ar fhreagra

Freagraí scríofa

In 2017, 25,901 households had their housing need met, with some 7,095 of these properties delivered under through the build/acquisition and long-term leasing mechanisms.

A total of 1,014 new build homes were delivered directly by local authorities. In addition, 761 new build homes were delivered by Approved Housing Bodies and a further 522 new build Part V homes were provided by local authorities and approved housing bodies, bringing to 2,297, the total of new build homes provided in 2017. A breakdown by local authority is set out in the Table.

-

LA New Build

AHB New Build (CAS and CALF)

Part V -New Build (All delivery streams)

Total New Build

Carlow County Council

43

0

10

53

Cavan County Council

2

0

1

3

Clare County Council

0

28

4

32

Cork City Council

33

0

0

33

Cork County Council

123

9

7

139

Donegal County Council

11

0

0

11

Dublin City Council

295

214

56

565

Dún Laoghaire-Rathdown County Council

38

0

137

175

Fingal County Council

99

54

101

254

Galway City Council

0

23

34

57

Galway County Council

31

23

0

54

Kerry County Council

10

0

0

10

Kildare County Council

28

66

24

118

Kilkenny County Council

29

19

3

51

Laois County Council

0

0

1

1

Leitrim County Council

0

2

0

2

Limerick City and County Co

111

7

9

127

Longford County Council

14

7

0

21

Louth County Council

25

93

1

119

Mayo County Council

3

7

0

10

Meath County Council

16

101

23

140

Monaghan County Council

39

7

5

51

Offaly County Council

5

0

0

5

Roscommon County Council

16

0

0

16

Sligo County Council

8

0

6

14

Sth Dublin County Council

0

45

80

125

Tipperary County Council

1

12

0

13

Waterford City and County Council

4

10

13

27

Westmeath County Council

21

2

0

23

Wexford County Council

9

32

6

47

Wicklow County Council

0

0

1

1

TOTALS

1,014

761

522

2,297

The significant expansion of the social housing build programme is evident in the Quarter 4 2017 Social Housing Construction Status Report, which was published on 19 April.  The programme includes 846 schemes (or phases) at the end of last year, delivering over 13,400 homes, a very substantial increase on the 8,430 homes in the programme a year earlier.  The full report can be accessed at http://rebuildingireland.ie/news/minister-murphy-publishes-social-housing-construction-status-report-q4-2017/.

Barr