Schools Refurbishment

Dáil Éireann Debate, Wednesday - 4 July 2018

Wednesday, 4 July 2018

Ceisteanna (239)

Bernard Durkan

Ceist:

239. Deputy Bernard J. Durkan asked the Minister for Education and Skills the extent to which he expects to progress the school building improvement and summer scheme programmes in respect of all schools in County Kildare at primary and second level with particular reference to those schools that have made submissions in this regard; and if he will make a statement on the matter. [29694/18]

Amharc ar fhreagra

Freagraí scríofa

My Department's Capital Programme (2016-2021) continues to address the challenges posed by the significant bulge in pupil enrolments going through our schools. This has seen a significant expansion in the rate of provision of new school places. The Capital Programme details the school projects that are being progressed through the architectural planning process, including those schools in County Kildare. The Capital Programme also provides for devolved funding for additional classrooms, if required, for schools where an immediate enrolment need has been identified or where an additional teacher has been appointed.

I wish to advise the Deputy that my Department has set out on its website at www.education.ie - Building Works, the current status of building projects and this is updated regularly.

I also wish to advise the Deputy of my announcement in April regarding the establishment of 42 new schools over the next four years (2019 to 2022). This announcement follows nationwide demographic exercises carried out by the Department into the future need for primary and post-primary schools across the country, including County Kildare and the 4-year horizon will enable increased lead-in times for planning and delivery of the necessary infrastructure.

In addition to the new schools announced, there will be a need for further school accommodation in other areas in the future. Based on the current analysis, this need can be addressed through either planned capacity increases in existing schools or additional accommodation or extensions to existing schools.

The Summer Works Scheme (SWS) is a multi-annual Scheme. Over 1,650 schools, nearly 50% of schools, applied for inclusion under the current round of the scheme which reflects a very high demand.

To date, almost €80 million has been approved under the current round of the Scheme, in respect of 635 school projects, 464 primary and 171 post-primary schools, for Gas, electrical upgrades, mechanical, sanitation and roof improvement works. Details of the successful school applicants, are published on the Department's website www.education.ie.

In relation to the SWS 2018, over €25 million will be spent on summer works projects in 2018. This expenditure will enable the remaining approved improvement works for 178 schools nationwide to be completed. These works will be carried out by the schools themselves on a devolved basis mainly over the summer months, so the disruption to students, teachers and other school staff will be kept to a minimum.

Furthermore, the Department intends to engage with the relevant education partners in relation to giving schools a better lead-in period for planning and delivering projects under the summer works scheme from 2019 onwards. While the SWS is hugely successful in enabling small scale refurbishment works to be done on a devolved basis, the Department considers that the operation of the scheme could be improved by providing a better lead-in period for schools rather than in Quarter 2 as in previous years. This will also help ensure that works done under the SWS fit better with any wider refurbishment/energy retrofit plans that may be done at schools under the increased funding provided in the National Development Plan. The engagement with education partners will commence shortly and will assist in developing a better timeline for the planning and delivery of summer works projects for 2019 onwards.