243. Deputy Pearse Doherty asked the Minister for Education and Skills the status of a school building project (details supplied) in County Donegal; when the project is likely to proceed to construction; and if he will make a statement on the matter. [29701/18]

Amharc ar fhreagra

Freagraí scríofa

The major building project referred to by the Deputy is currently at Stage 1 of the Architectural Planning Process.

Stage 1 is the Preliminary Design Stage where the Design Team in conjunction with the school authority will analyse all the constraints of the site, develop a preferred design option and ensure that the preferred option is the best option for the delivery of the brief. The school's design team will present their design proposals to the school and the Department for approval.

The project will then progress through the remaining stages of architectural planning which includes detailed design, the planning application and other statutory approvals and the preparation of tender documents. This project is included in the 6 year construction programme and is scheduled therein to go to construction 2019 - 2021. When the design stages are completed and planning permission and the other statutory approvals have been secured my Department will be able to provide the school with a more definitive timeframe for the tender and construction stages of the project.