Schools Building Projects Status

Dáil Éireann Debate, Friday - 7 September 2018

Friday, 7 September 2018

Ceisteanna (349)

James Lawless

Ceist:

349. Deputy James Lawless asked the Minister for Education and Skills the status of the building project at a school (details supplied) in County Kildare; and if he will make a statement on the matter. [36668/18]

Amharc ar fhreagra

Freagraí scríofa

The major building project referred to by the Deputy is currently at Stage 2b – Detailed Design.

This project was authorised to commence the Pre-Qualification of Contractors in May 2018.  My Department has been informed that the Design Team Leader published the contract notice inviting contractors to tender for Pre-Qualification on e-tenders on 2 August 2018 with a closing date for receipt of submissions of 10 September 2018.  The pre-qualification and shortlisting of suitable contractors normally takes between 8 and 12 weeks to complete.

When pre-qualification is complete the project will then be progressed to tender stage. A tender stage normally takes between 7 and 8 months to complete.

In March 2018 my Department issued a letter to the school and its Design Team outlining the projected timeframe for the progression of this project to tender and construction stage and the steps involved.