Dáil Éireann Debate, Tuesday - 6 November 2018

Tuesday, 6 November 2018

Ceisteanna (342)

Fiona O'Loughlin

Ceist:

342. Deputy Fiona O'Loughlin asked the Minister for Education and Skills if his Department received a report (details supplied) in relation to a school; and the action taken when this report was received. [45486/18]

Amharc ar fhreagra

Freagraí scríofa

I can confirm that the report referred to by the Deputy was received in my Department in May 2018. The report was referred to the Consultant Architect engaged on the project who subsequently arranged for the original contractor to carry out the necessary repairs over the summer holiday period.

My Department has received confirmation from the Architect that all necessary remedial works were completed by the end of July 2018.